Finnish grid and nuclear plant in dispute over power backup

Published 05/10/2023, 10:21
Updated 05/10/2023, 10:25
© Reuters.

By Anne Kauranen

HELSINKI (Reuters) - Finland's energy authority says it will rule "as soon as possible" on a dispute between the owners of Europe's largest nuclear reactor and national grid operator Fingrid over the cost of power backup for the 1.6 gigawatt (GW) reactor.

Finland's Olkiluoto 3 (OL3) nuclear reactor started regular power production in April after 18 years of construction and testing, and years of legal battles over costs and delays.

Now the owners - the TVO consortium that includes utility Fortum, chemicals producer Kemira, and forestry groups UPM and Stora Enso among others - have accused Fingrid of setting "unfounded restrictions" on OL3's power generation, the energy authority said.

In an official complaint, TVO is asking for an investigation into whether Fingrid has neglected its obligations to develop the grid, the authority said, adding it would rule on the matter "as soon as possible".

Whenever OL3's production exceeds 1.3 GW, Fingrid requires TVO to keep sufficient power backup capacity instantly available in case of a technical failure that could otherwise black out the national grid.

TVO's owners are big industrial power consumers that lower their own production to provide the system backup but are unable to do so, for example, during maintenance shutdowns, TVO said.

"During the past months, OL3's output has often been reduced because the backup capacity has not been fully available," TVO's head of communications Johanna Aho told Reuters.

TVO wants a different kind of backup system "to match today's needs", she added.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Fingrid says it represents the public interest and power end-users who would eventually pay the bill for new investments in national power backup capacity.

"This discussion is all about money," Fingrid's Chief Executive Jukka Ruusunen told Reuters.

The existing backup arrangement was made 20 years ago when planning for OL3 construction began and reserve capacity had little financial value. Now TVO's reserves are worth 100 million euros annually in the reserve markets, he said.

"Now they have come up with an idea that Fingrid should build a new kind of protection at the expense of power users," Ruusunen said.

OL3 accounts for around 14% of Finland's overall power demand.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.