(Reuters) -British power generator and network operator SSE (LON:SSE) kept its annual profit forecast on Thursday, but warned one of its major projects may face a delay to full operations.

The company, which reiterated its adjusted earnings per share forecast for the full year ending in March of more than 150 pence, said challenging weather and operational conditions that saw 10 named storms hurt its renewables output in the third quarter of 2023.

The company also said its Dogger Bank A offshore wind farm may not be fully operational until 2025 rather than this year as initially expected.

It said challenging weather, availability of vessels and supply chain delays had slowed its development.

The project is expected to have a total capacity of 1.2 gigawatts, capable of powering around 2 million homes.

SSE said the delay would not materially change the project's returns.

Shares in the company, which have gained more than 8% in 2023, were trading down almost 2% at 1,620 pence at 1022 GMT.