BP assessing New York wind projects after $540 million writedown, CEO says

Reuters

Published Oct 31, 2023 08:06

Updated Oct 31, 2023 16:30

LONDON (Reuters) -BP remains committed to its offshore wind growth plans after the energy company booked a $540 million impairment on two U.S. projects, CEO Murray Auchincloss told Reuters on Tuesday.

BP (LON:BP) and its partner Equinor are assessing their next steps after the state of New York rejected the companies' request to revise upwards power supply contracts for the giant projects, Auchincloss said.

The pretax impairment on the projects was due to "inflationary pressures and permitting delays," BP said.

Norway's Equinor booked a $300 million impairment on the projects last week.

"New York put out a 10-point plan, which would help move these projects forward... We'll be looking at that with our partner Equinor and deciding what we do moving forward," he said, after BP reported third-quarter earnings of $3.3 billion.